Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
SCHEDULE 4 DELIVERABLE

Quality Management Plan
& Inspection Regime

Document numberDTL-PRJ0072-QMP-001
RevisionA — Issued for Approval
Date16 July 2026
AttentionMr John Stephens — Principal Representative
Contract · Purchase orderSBS10627 · PO 182113
Scope of work23092-SOW-024rD (incl. Manufacturers Data Report)
StandardsAS/NZS 4130 (HDPE) · DTL QMS (working toward ISO 9001)
Submitted underContract Schedule 4 — required pre-mobilisation
DTL (WA) Pty Ltd  ·  2/28 Horus Bend, Bibra Lake WA 6163  ·  ABN 45 677 646 454  ·  Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

§Document control

Revision history

RevDateDescription of changeByChkApp
A16 Jul 2026Issued to SBR for review & approvalSHTK 
      
HOLD — SBR Construction Quality Control procedure. SOW requires the Manufacturers Data Report to be compiled “in accordance with SBR’s Construction Quality Control procedure”. DTL has not been provided this procedure. This Plan is built to AS/NZS 4130 and DTL’s QMS; it will be reconciled to SBR’s procedure on receipt. Please provide it.

Approval

PREPARED — DTL
Sean Heron
Project Manager · Date
AUTHORISED — DTL
Tyson Knight
Director & Contractor Representative · Date
REVIEWED — SBR
Principal Representative · Date
APPROVED — SBR
for mobilisation · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

§Contents

1Purpose & quality objective2Standards & the DTL quality system3Roles & responsibilities4Inspection & Test Plans (ITPs)5HDPE weld quality & traceability6Materials control & traceability7Non-conformance & corrective action8Calibration of test & measuring equipment9Manufacturers Data Report (MDR)10Records, handover & supporting documents
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

1Purpose & quality objective

This Quality Management Plan (QMP) sets out how DTL (WA) Pty Ltd will plan, verify and record quality for the Bitterns Recycling Field Piping Installation, so that the completed Works meet the contract, AS/NZS 4130 and SBR’s requirements, and so a complete Manufacturers Data Report can be assembled and handed over. It is a Schedule 4 deliverable, submitted pre-mobilisation, and supplements DTL’s Quality Policy (DTL-QA-POL-0001).

The quality objective: every weld and every material traceable, every inspection point recorded, zero un-closed non-conformances at handover.

2Standards & the DTL quality system

DTL applies the plan–do–check cycle: plan the inspection and test points (ITP), do the work, verify at each point against acceptance criteria, record the result, and release only on conformance.

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 4 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

3Roles & responsibilities

Contractor RepresentativeOverall accountability for quality delivery and MDR submission.
Site SupervisorEnsures ITPs are followed, hold points released before work proceeds, and records captured daily.
HDPE Fusion OperatorWelds to the approved parameters; completes the Daily Weld Register and Heater Plate Check each shift.
Quality (Management)Maintains the ITP register, NCR register and calibration register; compiles the MDR.
SBR / Principal RepresentativeAttends witness/hold points as elected on the ITP; reviews and accepts quality records.

4Inspection & Test Plans (ITPs)

Each work activity is covered by an ITP that lists every inspection/test point, its acceptance criteria, the record produced, and who signs. Hold points stop work until released; witness points invite attendance but do not stop work if unattended. ITPs follow DTL-QA-PRO-0002.

4.1 ITP register for this project

ITPActivityKey points
ITP-01Material receivalCoC & AS/NZS 4130 cert check; damage/UV inspection; traceability recorded (H)
ITP-02HDPE butt fusionParameters, heater plate temp, weld log per joint; bead inspection (H)
ITP-03Stringing & installationAlignment, cover, road crossings, mounding to drawing (W)
ITP-04Tie-ins, ARV & flanged jointsTorque, gasket, alignment; connection record (H)
ITP-05Pressure / leak testTest pressure, hold time, pass criteria; test certificate (H)
ITP-06Handover & MDRWeld map complete; all records closed; MDR compiled (H)
(H) hold point  ·  (W) witness point. SBR may elect to attend any point. The detailed HDPE ITP (points, criteria, sign-off) is issued separately as DTL-PRJ0072-ITP-001.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 5 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

5HDPE weld quality & traceability

Butt-fusion is the critical quality activity. Every joint is welded to approved parameters and recorded, so that each weld is traceable to its operator, machine, materials and parameters — the backbone of the MDR.

Record (per shift / per weld)DocCaptures
Poly Welding ParametersDTL-HDPE-TEM-0003Approved fusion parameters for each pipe size/class.
Daily Heater Plate CheckDTL-HDPE-TEM-0001Heater plate temperature verified before welding each shift.
Daily Weld RegisterDTL-HDPE-TEM-0002Every joint: weld no., operator, machine, materials, parameters, pass/fail.
Weld mapproject drawingEach weld number located on the pipeline drawing — complete traceability.
Capture as you go. The MDR’s weld registers and weld mapping are built during the works, weld by weld. If weld records are not captured each shift, the MDR cannot be assembled at Completion. The Daily Weld Register is a mandatory daily record from the first joint.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 6 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

6Materials control & traceability

7Non-conformance & corrective action

Any work or material not meeting requirements is raised as a Non-Conformance Report (DTL-QA-PRO-0001), logged in the Non-Conformance Register (DTL-QA-REG-0001), dispositioned (use-as-is / rework / repair / reject) with SBR where required, and closed with corrective action to prevent recurrence. No NCR is left open at handover.

8Calibration of test & measuring equipment

Test and measuring equipment used for acceptance (pressure gauges, temperature and fusion-machine instrumentation) is calibrated and in date, per DTL-QA-PRO-0003, with status recorded in the Calibration Register (DTL-QA-REG-0002). Calibration certificates are included in the MDR.

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 7 of 12
Quality Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-QMP-001
Rev A

9Manufacturers Data Report (MDR)

DTL compiles the MDR during the Works and submits it to SBR within two weeks of Completion, in accordance with SBR’s Construction Quality Control procedure (see HOLD, page 2). The MDR includes, but is not limited to:

#MDR content (per SOW)Source record
1Manufacturer’s Certificates of Conformity (CoC)Supplier, on receival
2AS/NZS 4130 compliance certificates for all HDPE pipeworkSupplier, on receival
3HDPE pipe & fitting material traceability recordsReceival log
4Factory inspection & test recordsSupplier
5Product datasheets for all supplied itemsSupplier
6Pressure-rating certificationSupplier
7Installation, handling & storage recommendationsSupplier / DTL
8Welding & jointing proceduresDTL-HDPE-TEM-0003
9Weld registers & weld mapping (complete traceability)DTL-HDPE-TEM-0002 + weld map
10Welder qualificationsPersonnel matrix (DTL-PRJ0072-HSE-002)
The MDR is assembled continuously through the job, not written at the end — every record above is generated as the Works proceed and filed against its weld or delivery on capture.

10Records, handover & supporting documents

Quality records are retained on the job file and in DTL’s system (2iB). Supporting documents:

Doc No.Document
DTL-QA-POL-0001Quality Policy
DTL-QA-PRO-0001Non-Conformance & Corrective Action Procedure
DTL-QA-PRO-0002Inspection & Test Plan (ITP) Procedure
DTL-QA-PRO-0003Calibration Procedure
DTL-QA-REG-0001 / 0002Non-Conformance / Calibration registers
DTL-HDPE-TEM-0001/0002/0003Heater Plate Check / Daily Weld Register / Poly Welding Parameters
DTL-PRJ0072-ITP-001HDPE Inspection & Test Plan (issued separately)
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 8 of 12